Modernisation of electrical installations and industrial lighting for mining companies JSW and PGG — where reliability, safety compliance, and zero disruption to operations define every decision.

WYNIKI PROJEKTU

Kluczowe liczby z tej realizacji.

Contract value

58,34mln PLN

Clients

JSW · PGG

Scope

Electrical & LED

Safety

Heightened BHP

Context & Challenge

In an industrial environment, modernisation cannot disrupt facility operations. Lighting and power supply infrastructure must function reliably, and works must be conducted under elevated health and safety requirements and facility procedures. Equally critical is reducing maintenance costs and failure rates — because downtime is a real cost.

Scope & Solution

The scope included modernisation of electrical power installations, switchgear and power supply infrastructure works, and replacement of industrial lighting systems with LED — depending on the facility's needs. Implementation was conducted in stages, with emphasis on safety, work documentation, and maintaining the required technical standard.

Outcome

Deliveries for the mining sector confirm Linter Energia's competencies in working with infrastructure under elevated requirements — where quality, predictability, and execution responsibility matter most. This experience also strengthens municipal projects by transferring the organisational and technical standards typical of industry.

ZAKRES REALIZACJI

Zastosowane technologie i urządzenia.

The requirements in the mining sector are uncompromising. Linter Energia delivered an installation that met every safety standard — on time, without a single disruption to our operations.

JSW / PGG – Industrial Sector 1
JSW / PGG – Industrial Sector 2
JSW / PGG – Industrial Sector 3
JSW / PGG – Industrial Sector 4
JSW / PGG – Industrial Sector 5
JSW / PGG – Industrial Sector 6
JSW / PGG – Industrial Sector 7
JSW / PGG – Industrial Sector 8
JSW / PGG – Industrial Sector 9
JSW / PGG – Industrial Sector 10