Gmina Bolesław – Lighting Modernization

The project involved the modernization of road lighting infrastructure using energy-efficient LED LINTER CONTROL technology. The work also included adapting the installation to modern energy management standards.

WYNIKI PROJEKTU

Kluczowe liczby z tej realizacji.

Contract value

~600 k PLN

Luminaires installed

318

Procurement

Open tender

Year

2024-2025

Context & Challenge

The project carried out in Gmina Bolesław aimed at modernizing the street lighting system by replacing existing lamps with energy-efficient LED fixtures. The key challenge was to improve the energy efficiency of the system and update the infrastructure to include modern lighting control capabilities.

Scope & Solution

The investment included the supply and installation of 318 LED fixtures with power cables and safety enclosures. The project also involved the modernization of the control cabinets, electrical installation measurements, and the preparation of necessary documentation to ensure compliance with technical requirements.

Outcome

The result of the project is an improvement in street lighting quality and an increase in the energy efficiency of the system. The modernization of the control infrastructure enables more effective management of the lighting system and contributes to enhancing user safety.