PROJEKTERGEBNISSE
Kennzahlen aus diesem Projekt.
Contract value
~600 k PLN
Luminaires installed
318
Procurement
Open tender
Year
2024-2025
Context & Challenge
The project carried out in Gmina Bolesław aimed at modernizing the street lighting system by replacing existing lamps with energy-efficient LED fixtures. The key challenge was to improve the energy efficiency of the system and update the infrastructure to include modern lighting control capabilities.
Scope & Solution
The investment included the supply and installation of 318 LED fixtures with power cables and safety enclosures. The project also involved the modernization of the control cabinets, electrical installation measurements, and the preparation of necessary documentation to ensure compliance with technical requirements.
Outcome
The result of the project is an improvement in street lighting quality and an increase in the energy efficiency of the system. The modernization of the control infrastructure enables more effective management of the lighting system and contributes to enhancing user safety.