PROJECT RESULTS
Key numbers from this project.
Contract value
~2.8mln PLN
Luminaires installed
2 575
Procurement
Open tender
Year
2024–2025
Context & Challenge
The city expected visible improvement in public lighting quality while simultaneously reducing operating costs. In practice, this meant carrying out works at multiple locations while maintaining infrastructure continuity and meeting formal requirements: from luminaire parameter compliance to proper organisation of acceptance procedures.
Scope & Solution
Linter Energia executed the project covering replacement of road and park luminaires with LED, based on tender requirements and technical specifications (SWZ/OPZ). The scope also included ancillary works on power supply and equipment, with the final stage comprising post-installation measurements and technical acceptance. The implementation was planned to minimise disruptions and maintain lighting continuity at critical points throughout the city.
Outcome
The result is a more modern and efficient lighting system: better visibility and comfort for road users after dark, lower energy costs, and simpler infrastructure maintenance. The project confirmed the company's experience in delivering municipal investments through public procurement — from formal compliance to ensuring quality and final parameters.